Hi All
I have found that to correct an earlier issue I had with MF60 I need to activate/process a PCN. However, I am not getting a PCN generated when I stage materials.
I have been told that this is SAP standard. Therefore, where is the missing config in SPRO?
As an overview.....
I have 1 plant, 1 warehouse and 2 storage locations.
SLoc 1 is where I am drawing stock from
SLoc 2 is the production area
I run MF60 to pull stock from SLoc 1.
Following the creation of the TR I should get a PCN asking me where I should place the stock in SLoc 2
Am I understanding the process correctly.
I am usually OK with working through processes but this is proving difficult to get my head round!
Thanks in advance for any assistance
Darren